Stacy Witbeck is the managing joint venture partner on this GC/CM contract for a 4.8-mile double-track extension of Sound Transit’s light rail system. The alignment is in a narrow corridor parallel and adjacent to Interstate 5. The route consists of 1.9 miles of elevated guideway with direct fixation track, and three miles of ballasted track in an at-grade guideway on retained cuts/fills. cuts/fills.
Significant obstacles were overcome to complete on schedule, including challenging weather events, such as unusually heavy rains, snow, and wildfires. There was also a local concrete strike, as well as the global pandemic starting right as construction was set to begin.
The team found solutions to navigate these hurdles, coordinating schedules to start systems work before construction was completed. To build in this tight corridor, a temporary trestle with oscillating drill rigs and cofferdams over a wetland was built, along with a cast-in-place overpass requiring 200 shafts up to 20 feet in diameter and 80 feet deep.
The scope included two stations, infrastructure for a future third station, and two large parking garages. Other work was demolition, clearing and grubbing, utility relocations, extensive retaining walls, site work, civil aspects of systems work, road work, site improvements around stations, stormwater retention facilities, and restoration.
Seattle, WA
Bridges and Highways, Light Rail, Parks & Public Spaces
CM/GC
2024
Sound Transit
Northwest